Highway 225 Bridge Waterline Relocation

Client

West Stone County Water Association

Completion

November 2022

Location

Stone County, AR

Crafton Tull was contracted by West Stone County Water Association for the relocation of approximately 1,500 LF of waterline due to the Highway 225 improvements.

Prior to the relocation, the existing waterline was leaking, and the lost water was creating a financial hardship for West Stone County Water. A 4” temporary waterline was installed along the bridge deck due to the failing existing waterline installed along the lake bottom. The temporary solution allowed time for the permanent 8” ductile iron waterline to be affixed to the bottom of the bridge structure while providing continuous service to the system.

Crafton Tull prepared the construction documents and conducted construction administration for the project.

Client

West Stone County Water Association

Completion

November 2022